MD04 - Rescheduling Date in Past

$
0
0

Hello,

 

I have a question regarding a material (HAWA)  in MD04.  The "Rescheduling" date is in the past with the exception of 10.

 

Current Status of material:

 

  • Stock on hand = 2
  • IndReq = 11
  • PO Item = 2,544

 

I was expecting our nightly MRP to look at this PO and set the "Rescheduling" date to the current date or to the last time MRP executed.

 

I have attached a screen shot hoping this will help.

 

Question:  Does anyone know why this material would not be "Rescheduled" for the current date and subsequently update as MRP runs?

 

Thanks for the help.

 

JVH