Re: MD62 planning question

$
0
0

Hi Rahul,

Thank you for taking the time to help me.  In MD62 I selected "Reqmts Plan" and entered my customer name.  The date field I put in 8/1/2015 to 12/15/2015 and on the next screen I entered all my items and quantities forecasted for each month.  I then went up to Edit and selected Period Splitting which I selected weekly for the month of August. 

I need to reverse that and put it back to 08/2015 (I don't want to see the weekly buckets) but no one knows how to reverse this.

I hope I explained this better but if you need additional information, just let me know.

thank you again.